PrimeTest 250
+
Operating Instructions
33
Mains status
No mains
Earth fault
LN LE NE
Flash Flash OFF
OFF Flash Flash
Whenever reSet is displayed on the LCD press the
reset button on the RCD.
The PrimeTest 250
+
will perform a IΔn (30mA) 0°
test, the operating time of the RCD will be shown on
the PrimeTest 250
+
LCD. If the test passes then the
PrimeTest 250
+
will perform a IΔn (30mA) 180° test. As
long as the tests continue to pass the PrimeTest 250
+
will continue to test both 0° and 180° at IΔn (30mA).
3.10 Performing a 3-Phase Sequence
The PrimeTest 250
+
can be used to measure R
PE
and earth leakage current on 3 phase equipment
when used with the optional 3 phase adaptor
accessory.
Visually inspect the appliance and mains cord
for signs of damage.
If the appliance passes a visual inspection
proceed with the electrical tests.
Refer to the documentation supplied with the 3
phase adaptor and connect the adaptor in line
with the 3 phase equipment under test.
Connect the 3 phase adaptor test lead to the
mains input socket 9 (refer to fi gure 2) on the
PrimeTest 250
+
.
• Connect the R
PE
test probe to an exposed
conductive part on the 3 phase equipment.
Press the 3 phase key on the PrimeTest 250
+
to being the test.
If there is a contact voltage present on the
conductive parts of the equipment under test,
the test is terminated and a Volt on test Probe
warning message is shown on the display.